Solution

Construction Preparation

1. Determination of construction section measurement

According to the design width of the roadbed, put out the roadbed edge line, in order to ensure the effective compaction of the roadbed and the stability of the slope, when putting out the roadbed edge line should make the two sides of the line is 20cm-40cm wide appropriate.

2.Measurement of soil water content

① Use measuring tools to obtain accurate values;

② Take soil on site and heat it up using a frying pan, record the weight before and after heating and calculate the soil water content;

③ Take the soil on site and add water to do the test, the soil can be held in the hand into a ball and no water seepage, 1 meter in the air falling soil scattered that is to reach the optimal moisture content.

Note: If the water content of soil is too high, it needs to be dried, and the best water content of soil after spraying the product is 10%-15%.


Construction Steps

1. Soil Excavation
1. Soil Excavation

Excavate the road surface to the depth required by the design (20 cm for normal roads and 30 cm for heavy haul roads) using a plow or excavator and use a soil mixer to pulverize the soil, if there are larger stones that need to be picked out manually, gravel (≤30 mm) need not be treated and can strengthen the road.


2.Dilute Spraying Stabilizer
2.Dilute Spraying Stabilizer

The product is diluted with water and mixed well, which can be done in the sprinkler. In the case of suitable soil moisture content according to the ratio of 1:5 water, the actual dilution ratio can be adjusted according to the site soil composition and moisture content. Use sprinkler to evenly spray the diluted soil stabilizer water solution onto the road surface.


3. Mix The Product And Road Setting
3. Mix The Product And Road Setting

Immediately after spraying, use a soil mixer to fully mix the product and soil, so that it evenly contacts the soil. Level the soil according to the requests for road shaping.

4.Road Compaction
4.Road Compaction

Compact within 15 minutes of spraying the product. It is recommended to use sheep horn roller for compaction first, and then use vibratory roller for compaction. The type of roller and the number of rolling times depend on the site conditions, to achieve the maximum compaction density and maximum CBR value for the ultimate goal.